Airport Link Project changes
Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Airport Link Project.
Project change application 3 – Reporting requirements
| Date | Activity |
|---|---|
| 31 January 2014 | Coordinator-General's report on project change ( |
| 21 January 2014 | Proponent's project change application ( |
Project change application 2 – Wooloowin worksite modification
| Date | Activity |
|---|---|
| 29 October 2009 | Coordinator-General's report on project change ( |
| 19 August 2009 | Proponent's response to submissions ( |
| 19 July 2009 to 24 July 2008 | Project change application public consultation. |
| 20 July 2009 | Independent engineering report – GM Peck and Associates ( |
| 17 June 2009 | Proponent's project change application (
|
Project change application 1 - Local content strategy
| Date | Activity |
|---|---|
| 29 July 2008 | Coordinator-General's report on project change (
|
| 21 July 2008 | Proponent's response to submissions ( |
| 29 May 2008 to 31 May 2008 | Project change application public consultation. |
| 28 May 2008 | Proponent's project change application ( |
Last updated: 16 Mar 2023