Lower Fitzroy River Infrastructure Project
Project overview*
| EIS status | Approved with conditions |
| Description | The raising of Eden Bann Weir and construction of a new weir at Rookwood on the Fitzroy River, Central Queensland. |
| Proponent | SunWater Ltd. |
| Location/s |
|
| Local governments | The project is located predominantly within the Livingstone Shire and Rockhampton Region local government areas (LGAs), but also borders the Central Highlands Region and Woorabinda Aboriginal Shire LGAs. |
| Investment | $495 million (2014 dollars). |
| Key features |
|
| Jobs | 150 direct, peak construction and 5 direct operational jobs. |
* Project information supplied by proponent and subject to change.
Project changes
Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for changes to the Lower Fitzroy Infrastructure project.
Read more about the project changes.
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| 23 September 2024 | The Coordinator-General stated a new lapse date for the Coordinator-General's EIS evaluation report of 8 December 2028. |
| 2 December 2022 | The Coordinator-General stated a new lapse date for the Coordinator-General’s EIS evaluation report of 8 December 2024. |
| 11 November 2019 | The Coordinator-General stated a new lapse date for the Coordinator-General’s EIS evaluation report of 8 December 2022. |
| 28 February 2017 | Australian Minister for the Environment’s approval of 'controlled action', subject to conditions. |
| 8 December 2016 |
Coordinator-General's report on EIS ( |
| 14 September 2016 | The Coordinator-General accepted the revised draft EIS and the AEIS Addendum as the final EIS. |
| 9 August 2016 |
An Addendum ( |
| 28 May 2016 to 27 June 2016 | Additional information to the draft EIS (AEIS) public consultation. |
| 24 December 2015 | Coordinator-General amended the project declaration lapse date from 3 March 2016 to 23 December 2016. |
| 6 November 2015 | Revised draft EIS requested by Coordinator-General. |
| 18 July 2015 to 31 August 2015 | Draft EIS public consultation |
| 3 September 2014 | Revised final terms of reference ( |
| 19 July 2014 to 18 August 2014 |
Revised draft terms of reference ( |
| 10 March 2014 | Coordinator-General stated a new project declaration lapse date of 30 October 2014. |
| 27 April 2012 | Final terms of reference for EIS ( |
|
12 November 2011 to 16 December 2011 | Draft terms of reference for EIS public consultation. |
| 6 May 2011 |
Gazettal of 'coordinated project' declaration ( |
| 9 November 2010 |
Application, including initial advice statement ( |
| 7 January 2010 |
Australian Minister for the Environment decided the project is a 'controlled action'.
|
| 22 October 2009 | Project referred to Australian Minister for the Environment. |
Read more about the EIS process.
Further information
For more information, visit the Lower Fitzroy River Infrastructure Project website.
Last updated: 23 Sep 2024